Date of Hearing: September 15 & 17,
2003
Date of Decision: June 10, 2004
IN THE MATTER OF the Engineering, Geological and Geophysical
Professions Act
- and -
IN THE MATTER OF the conduct of [Engineer A], P.Eng. and
Robert Weldon, P.Eng. regarding environmental site assessment
services for [Company B]
1500 Scotia One, 10060 Jasper Avenue, Edmonton, Alberta,
Canada T5J 4A2
Tel: (780) 426-3990 Fax: (780) 426-1877 Toll Free: 1-800-661-7020
DISCIPLINE COMMITTEE PANEL Rick Imai, P.Eng., Chair
Bruce Alexander, P.Eng.
Allin Folinsbee, P.Geoph.
Panel Counsel Dwayne Chomyn, Neuman Thompson
PARTIES
APEGGA Investigative Committee represented by Barry Massing,
Hendrickson Gower Massing Olivieri
Members [Engineer A], P.Eng. and
Robert Weldon, P.Eng.
Members’ Counsel Mr. James R. Scott
Roddick, Scott & Johnson
BACKGROUND
On May 3, 2002, the Discipline Committee received, from
the Investigative Committee, the referral for a discipline
hearing concerning [Engineer A], P.Eng. and Robert Weldon,
P.Eng.
(the "Members"). The Discipline Committee responded
and requested that the Investigative Committee provide particulars
of the matters to be heard. The charges were received May
23, 2002. After obtaining the availability of all necessary
parties, a hearing date of November 12, 2002 was set.
On July 16, 2002, the Discipline Committee issued a formal
notice of hearing and served copies on the Members through
their counsel, Mr. Scott and on the Investigative Committee
(the "parties"). At the same time, the Discipline
Committee, according to its standard process for disclosure
of documents, requested that the parties provide, to the
Panel and to each other, copies of documents on which they
intended to rely at the hearing. Those documents were provided
to the Panel on November 6, 2002.
On November 8, 2002, Mr. Scott requested an adjournment
that the Investigative Committee did not oppose and new hearing
dates of April 9, 10 and 11, 2003 were set. On April 2, 2003,
the Investigative Committee and Mr. Scott both requested
another adjournment. The adjournment was granted, and subsequently
the hearing was rescheduled to begin September 15, 2003.
THE HEARING
The hearing was held before the Panel at the Association’s
offices in Edmonton on September 15, 2003 and reconvened
on September 17, 2003. Mr. Massing represented the Investigative
Committee. Mr. Scott represented Mr. Weldon and [Engineer
A]. Final submissions and closing arguments were made in
writing and put before the Panel on November 18, 2003.
CHARGES (ALLEGATIONS)
As noted in the formal hearing, the matters brought before
the Panel by the Investigative Committee related to the conduct
of Mr. Weldon and [Engineer A] in relation to services provided
regarding a series of Phase II Environmental Site Assessments,
6 in number, prepared for [Company B] by [Company C].
1. "That in or about July and August, 1998, [Engineer
A] authored a technical report, the content of which included
geophysical data and interpretive conclusions beyond the
training and expertise of [Engineer A], thereby constituting
unskilled practice of his profession and a breach of APEGGA
Code of Ethics Rule of Conduct No.2.
2. That in or about July and August, 1998, Robert Weldon
authored a technical report, the content of which included
geophysical data and interpretive conclusions beyond the
training and expertise of Robert Weldon, thereby constituting
unskilled practice of his profession and a breach of APEGGA
Code of Ethics Rule of Conduct No. 2."
On the first day of the hearing, it was agreed to amend
the charges to read:
R.V. Weldon, P.Eng.
1. That Mr. R.V.Weldon, P.Eng., signed and sealed several
technical reports as follows:
a) Report 6119-1, date November 23, 1998
b) Report 6119-2, date January 22, 1999
c) Report 6119-4, date January 22, 1999
d) Report 6119-5, date May 17, 1999
e) Report 6119-6, date May 17, 1999
f) Report 6119-8, date May 17, 1999
The contents of which included geophysical data and interpretive
conclusions beyond the training and expertise of R.V. Weldon,
P.Eng., thereby constituting either unskilled practice of
his profession or unprofessional conduct and a breach of
APEGGA Code of Ethics Rule of Conduct No. 2.
[Engineer A, P.Eng.]
1. That [Engineer A], P.Eng., as responsible professional
member for [Company C], signed and affixed the permit stamp
of [Company C] to the following reports:
a) Report 6119-1, date November 23, 1998
b) Report 6119-2, date January 22, 1999
c) Report 6119-4, date January 22, 1999
d) Report 6119-5, date May 17, 1999
e) Report 6119-6, date May 17, 1999
f) Report 6119-8, date May 17, 1999
The contents of which included geophysical data and interpretive
conclusions beyond the training and expertise of [Engineer
A], thereby constituting either unskilled practice of his
profession or unprofessional conduct and a breach of APEGGA
Code of Ethics Rule of Conduct No. 2.
FINDINGS
1. R.V. Weldon, P.Eng., authored, sealed, and signed six
reports that include EM-31 geophysical data in the form of
contour maps purporting to represent sub-surface levels of
conductivity. It is the opinion of the Panel that Mr. Weldon
did not have adequate knowledge, or training, in the use
of electromagnetic tools which are designed to provide an
estimate of terrain conductivity, to conduct an electromagnetic
survey and lacked the experience needed to ensure that data
was properly acquired and numerically valid.
The Panel finds that Mr. Weldon’s conduct constitutes
unskilled practice and a breach of APEGGA Code of Ethics
Rule of Conduct No. 2.
2. [Engineer A], P.Eng, signed and affixed the permit stamp
of [Company C] to six reports which include EM-31 geophysical
data in the form of contour maps purporting to represent
sub-surface levels of conductivity. It is the opinion of
the Panel that [Engineer A] was not required to have specific
experience, or training, in the use of electromagnetic tools
which are designed to provide an estimate of terrain conductivity,
and the data derived from them, in order to sign the permit
stamp since APEGGA does not require the signing member to
possess the specific training or expertise to support the
contents of the reports.
The Panel finds that [Engineer A’s] conduct does not
constitute unskilled practice or unprofessional conduct or
a breach of APEGGA Code of Ethics Rule of Conduct No. 2.
THE REASONS
1. Mr. Weldon and [Engineer A] are both charged with a breach
of APEGGA Code of Ethics Rule of Conduct No. 2 which states
that "Professional engineers, geologists and geophysicists
shall undertake only work that they are competent to perform
by virtue of training and experience and shall express
opinions on engineering, geological or geophysical matters
only on the basis of adequate knowledge and honest conviction.” (1995).
The Panel heard testimony from several witnesses and was
provided with a voluminous amount of written documentation
from both parties. Much of the material and testimony dealt
with the subject of geophysics and whether the use of the
electromagnetic tools to acquire terrain conductivity data
fell within the exclusive scope of practice of geophysics,
or was the use of these tools within the scope of practice
of geotechnical engineering. According to the Engineering,
Geological and Geophysical Professions Act [Part 1 section
7(1) ] “Subject to subsection (2) no individual,
corporation, partnership or other entity except a professional
geophysicist, a licensee so authorized in his license or
a permit holder so authorized in the permit shall engage
in the practice of geophysics”. However, given the
specific wording of the charge, the Panel felt its decision
must be based solely on the evidence pertaining to the
training and experience of Mr. Weldon and Engineer A and
how the EM-31 data contained in the reports, and the interpretations
arising from that data, are supported by their training
and experience. The Panel felt that the evidence provided
as to whether or not the use and interpretation of the
EM-31 data fell within the exclusive scope of practice
of geophysics was not the issue raised in the charge. The
question before the panel was whether the reports did contain
geophysical data and whether these members had the training
and experience to make proper and professional use of the
data in the context of the matters before the panel.
2. The subject reports were prepared by Mr. Robert Weldon,
P.Eng., as an environmental site investigation and baseline
survey of six former [Maintenance Yards]. The primary purpose
of the reports was to provide an assessment of the salt contamination
of the soils and the groundwater within the site. The format
and presentation for each report is similar and each essentially
contains borehole data, Oakton TDSTestr electrical conductivity
measurements, and an EM-31 survey. The EM-31 is an electromagnetic
device used by geophysicists to estimate the electrical conductivity
of the surface and subsurface down to a depth of 5 to 6 m.
This conductivity data can then be interpreted to indicate
areas of salt contamination.
The portions of the subject reports pertaining to the use
of the EM-31 consist of a brief description of the field
procedures used with the device, an appended contour plot,
and one or two observational interpretations in the conclusions
section. Mr. Weldon testified that he made no interpretations
from the EM-31data but it is clear that the some of the conclusions,
and the preparation of the contour maps, can only be as a
result of interpretations of the EM31 data.
For example in the report on the Ponoka site under Tab 11B,
page 8 it states “The EM contour map indicates that
the salt contamination extends to the north ... and appears
to extend to the northwest to just beyond the site boundary”.
It is simply not possible to draw this conclusion from the
soil sample data. Mr. Weldon did not even include a map in
the report showing the soil conductivities as measured in
the samples and cores. In his report under “Terrain
Conductivity Survey” he writes, “The EM-31 measures
soil conductivities in microSiemens/centimetre”. In
fact the EM-31 measures conductivities in milliSiemens /metre
(mS/m). Mr. Weldon then writes “ The resulting data
was input into a contouring program to generate a contour
map of the soil conductivity levels across the Site. The
contour map for the site is included as Figure 3, in Appendix
A.” There are no units specified on this contour map.
There is no explanation for the discrepancy between the conductivities
as measured in the test holes and the apparent conductivities
as seen on the EM contour map. For example Test hole 98-2
shows an average conductivity down to 5 m of 2600 microSiemens/centimetre
(uS/cm), and the EM contour map shows a value of about 60
at that location. Test hole 98-3 shows an average conductivity
down to 5 m of 270 uS/cm, and the EM contour map shows a
value of about 110. So at 98-2 the soil conductivities are
43 times larger than the EM contour map, and at 98-3 the
soil conductivities are 2.5 times larger than the EM contour
map.
The Panel felt that the interpretations presented in the
conclusions are only basic observational comments and that
these same conclusions could be drawn by the reader from
an examination of the contour plot without being stated
in the text. Hence, in the opinion of the Panel, a person
without training or experience could make these simplified
interpretations in geophysical surveying. However, the
Panel does consider that the field acquisition of the data,
and its refinement into the form of a contour plot, and
the inclusion of this map in the final report to the client,
would definitely require specific expertise to validate
the raw EM-31 readings and properly transpose them into
a contour plot.
3. The Investigative Committee presented testimony that
acquiring data by means of the EM-31 device and making interpretations
on that data, constitutes the practice of geophysics and
therefore is beyond the qualifications of Mr. Weldon and
[Engineer A] because they are not registered as geophysicists.
While their actions may be considered a violation of the
Engineering, Geological and Geophysical Professions Act,
this is not the basis of the amended charges.
4. The Panel heard from Mr. Weldon that the EM-31 was only
intended to be used as a tool to identify preferred locations
for subsequent conventional core drilling and soil sampling
techniques. He also indicated that he was not seeking exact
levels of conductivity but only relative values. The reports
however contain specific EM-31 references and detailed data
contour plots which go beyond the scope of preliminary borehole
screening and in fact, imply to the reader that they are
accurate measurements of ground conductivity. There were
no qualifications in the reports stating that the EM-31 results
were based on cursory field investigation procedures and
are not to be construed as accurate baseline measurements.
The Panel did not find fault with Mr. Weldon’s intent
to use the EM-31 as a preliminary screening tool but did
feel that if the EM-31 data and contour plots were only for
this purpose then it should not have been presented, or referenced
in the reports.
Mr. Weldon’s position that the EM-31 was only intended
to be used as a screening tool is not supported by his “revised” proposal
to [Company B] (dated May 22, 1998), that states that the
EM-31 services offered would permit the preparation of a
map showing the variations in electrical conductivity in
the ground. This component of the project was added at the
specific request of the client. There was no indication in
this proposal that the EM-31 would be used solely to determine
sampling locations or that the results were not intended
as baseline measurements.
5. Mr. Weldon testified that he had only minimal prior experience
with conductivity measurements and had no training with use
of the EM-31 device or the experience to judge the suitability
or accuracy of the raw data. He did retain Mr. Don Roy, an
experienced EM-31 technologist, to assist him with the field
data acquisition but testified that he relied on Mr. Roy’s
recommendations to establish the survey procedure including
the frequency and spacing of the readings and the background
levels of conductivity.
The Panel felt that Mr. Weldon relied too heavily on Mr.
Roy and that he should have had sufficient experience and
knowledge on his own to properly conduct the field program.
He should have been at least knowledgeable on the standard
measurement units used and the magnitude of typical background
values to be expected. Alternatively, Mr. Weldon should have
stated clearly the limitations of his experience and knowledge
and the limited purpose for which the data was purportedly
being used. This is not a mere clerical or reporting error.
The client requested that the firm use the EM-31. The natural
inference is that they wanted someone knowledgeable in the
use of and interpretation of the data.
6. The Panel heard evidence from the Investigative Committee
that the EM-31 contour plots in the reports were numerically
incorrect and that there are errors and inconsistencies
with the units as stated. Mr. Johnston testified that after
he converted the maps into the “correct” units
of mS/m then the low (background) values seem reasonable
but that the maximum values are too low, which could mean
they underestimated the amount of contamination on the
site by a very large factor. Mr. Weldon testified that
he was unsure of the units at the time of writing the reports
and that he was unable to contact the firm who supplied
the EM-31 device because it was no longer in business.
The Panel did not accept this excuse and felt that Mr.
Weldon should have exhausted other sources in order to
verify something as basic and essential as the units with
which he was working.
ORDERS
On March 26, 2004, the Panel served its findings and reasons
on the parties and requested them to provide written submissions
on orders. Both parties made submissions, and the Panel received
these on April 28, 2004. On May 4, 2004 the Panel requested
the Director of Professional Practice (the Director) to provide
information on the costs associated with the hearing. The
Director wrote to the parties on May 5, 2004, indicating
the costs that his office had determined and noting that
if the parties had no objections, he would provide a copy
of that letter to the Panel on May 12, 2004. Mr. Scott responded
with a request for a breakdown of the Investigative Committee
and Discipline Committee counsel services. The Director subsequently
provided that information. No further comments or objections
were received from either party, and the costs letter was
provided to the Panel on May 28, 2004.
Pursuant to the Panel’s findings and the submissions
made by the Investigative Committee and Mr. Scott, the Panel
makes the following orders:
1. That Mr. Weldon be reprimanded for unskilled practice.
2. That Mr. Weldon pay to APEGGA the amount of $ 4,814.67,
being 25% of the total costs of the hearing, such costs to
be paid within 60 days from the date of these orders being
served on him.
3. If Mr. Weldon fails to comply with Order 2 above, then
his registration in APEGGA shall be suspended until Order
2 above is complied with.
The Panel noted in the submissions from both parties that
Mr. Weldon has not been the subject of any previous disciplinary
actions and that the conduct in question did not compromise
public safety. The Panel agrees that a reprimand for unskilled
practice is appropriate.
In assessing a portion of the costs against Mr. Weldon,
the Panel has considered the reasons why [Engineer A] and
Mr. Weldon elected to proceed with this hearing, and the
Panel took note of the fact that there were no adverse findings
against [Engineer A]. The adverse findings of the Panel stemming
from the hearing were based solely on the actions of Mr.
Weldon. Accordingly, a sanction of 25% of the costs is deemed
appropriate.
DATED this 10th day of June, 2004 at Edmonton, Alberta.
___________________________________
Rick Imai, P.Eng.
Chair, Discipline Hearing Panel
Although there were no findings against one of the members
in this decision, and the committee itself did not order
publication, Council policy requires that The PEGG publish
all discipline committee decisions. One member’s name
and some other identifying words have been removed. Changed
material spears in side large brackets.
|