Engineering
played a decisive role in making the main railroad line between Alberta
and B.C. safer and more efficient.
The
original line between Hector and Field, B.C. had a 4.5 per cent grade
- meaning there was a change of 900 feet in elevation over just four miles.
It was an excessive slope for trains to maneuver. The slope was so steep
that four 154-ton locomotives were required to move just 710 tons of freight
up the hill, not an economical means of transporting goods.
The solution
to reducing the amount of slope meant artificially lengthening the route.
Spiral tunnels, which turned back around and underneath themselves were
the answer.
Between 1907
and 1909 the first two tunnels were built. More than one thousand men
laboured to remove more than 54,000 cubic metres of rock.
Tunnel #1 measures 3,255 feet long and turns 291 degrees; Tunnel #2 is
2,922 feet long and turns 217 degrees.
These spiral
sensations are the only tunnels of this kind in North America.
Links to
other resources:
|